As-built measurement

Short answer
Determining the quantities of work actually performed, which form the basis for payment. Distinct from the bill of quantities, which states the quantities planned before execution.

The bill of quantities answers the question how much we plan to build; the as-built measurement answers how much was actually built. A gap between those two numbers is a normal occurrence on an infrastructure contract; the problem is not the gap itself but the missing trail of where it came from.

A data model that holds up

For a measurement item to be billable without reconstruction, it needs at minimum:

boq_itemreferenceowner: Cost estimator

A link to the bill-of-quantities item — without it, the measurement is a loose number.

quantitynumber + unitowner: Works manager

The actual quantity, in the unit matching the BoQ item.

basistext / attachmentowner: Works manager

Where the quantity comes from: a sketch, a survey measurement, a protocol. This field decides whether the settlement is defensible.

date_and_locationdate + chainage/structureowner: Works manager

When and where — the link to the work front.

A missing "basis" field is the most common reason a measurement ends up being defended later from people's memory rather than from a document.

Sources

The substantive basis of this text. Items marked as own practice do not come from a document — they are delivery experience that cannot be verified with a publisher.

  1. DocumentGeneralny Dyrektor Dróg Krajowych i Autostrad / GDDKiA Oddział w Katowicach
    STWiORB DM.00.00.00 (GDDKiA technical specification, in Polish), item 7 — „Rejestr obmiarów” (the measurement register), continuous measurement in the units of the bill of quantities, permanent works measured net (pp. 31–32)
  2. DocumentGeneralny Dyrektor Dróg Krajowych i Autostrad / GDDKiA Oddział w Katowicach
    STWiORB (GDDKiA technical specification, in Polish) — the measurement unit and the scope of the unit price defined in items 7 and 9 of each detailed specification

Where we write about this

ComparisonJul 20, 2026 · 9 min

Excel or a custom application — where the break-even point lies

When a spreadsheet stops being enough in a construction process and how to tell. Decision criteria, hidden spreadsheet costs, and when a custom application pays off.

ArtifactJul 20, 2026 · 8 min

Construction dashboard: 12 data points that need an owner

A ready list of fields without which a construction management dashboard shows opinions instead of state. For each field: responsible role, source, and update frequency.